File #: 14-00255    Version: 1 Name:
Type: Motion Status: Filed with the City Secretary
File created: 2/28/2014 In control: City Council
On agenda: 3/18/2014 Final action: 3/25/2014
Title: Change order authorization for the Mary Rhodes Pipeline Phase 2 pipeline section A, B, and C and pump stations/sedimentation basin Motion authorizing the City Manager or designee to execute non routine change orders of up to 5% of the contract value, of (1) the construction contract with Garney Companies, Inc. for the Mary Rhodes Pipeline Phase 2: Pipeline Sections A, B, and C for $84,121,405, or (2) the construction contract with Oscar Renda Contracting for the Mary Rhodes Pipeline Phase 2: Pump Stations/Sedimentation Basin for $29,167,288, if changes in plans or specifications are necessary after the performance of the contract has begun or if it is necessary to decrease or increase the quantity of work to be performed or of materials, equipment, or supplies to be furnished, for reasons creating an urgent need for the change, including but not limited to differing site conditions, provided that (I) funding is available for that purpose; (II) the original contract price is not increa...
Sponsors: Engineering Services
Attachments: 1. Agenda Memo - MR Pipeline, 2. Location Map - MR Pipeline
Title
Change order authorization for the Mary Rhodes Pipeline Phase 2 pipeline section A, B, and C and pump stations/sedimentation basin
 
Motion authorizing the City Manager or designee to execute non routine change orders of up to 5% of the contract value, of (1) the construction contract with Garney Companies, Inc. for the Mary Rhodes Pipeline Phase 2: Pipeline Sections A, B, and C for $84,121,405, or (2) the construction contract with Oscar Renda Contracting for the Mary Rhodes Pipeline Phase 2: Pump Stations/Sedimentation Basin for $29,167,288, if changes in plans or specifications are necessary after the performance of the contract has begun or if it is necessary to decrease or increase the quantity of work to be performed or of materials, equipment, or supplies to be furnished, for reasons creating an urgent need for the change, including but not limited to differing site conditions, provided that (I) funding is available for that purpose; (II) the original contract price is not increased by cumulative change orders by more than 5 percent (5%) of the original contract price; (III) a report is provided to City Council as soon as possible afterward; and (IV) the Executive Director of Public Works has conducted a full review of the facts and determines, in writing, that: (a) the change is required and/or unavoidable, and (b) time is of the essence to the extent that immediate action must be taken in order (i) to avoid substantial delay damages from being incurred; or (ii) to prevent significant harm from occurring to the City's property or the City's Mary Rhodes Pipeline Phase 2 Project.