Title:
|
Motion authorizing a construction contract to CSA Construction, Inc., Houston, Texas, for the Oso Water Reclamation Plant (WRP) Process Upgrade & Breakpoint Chlorination (BPC) Facility Decommissioning project to replace the existing Breakpoint Chlorination (BPC) facility with biological ammonia removal treatment process, provides a third treatment basin and modifies the existing two treatment basins to increase the treatment capacity in an amount of $109,890,200.00 and an Amendment No. 10 to the Professional Services Contract with Ardurra Group Inc., Corpus Christi, Texas in an amount not to exceed $1,000,000.00 for a total amount of $11,048,529.00 for construction phase services, located in Council District 4, with FY 2024 funding available from the Wastewater Capital Fund.
|