Title:
|
Ordinance accepting and appropriating Airport Grant #58 in the amount of $9,445,368; awarding a contract in the amount of $6,884,574.42 with Airfield Contracting, a Joint Venture between Head, Inc. of Columbus, Ohio and Jackson Construction Services, LLC, of Jacksboro, Texas for the total base bid and additive alternates 1 and 2 for the Corpus Christi International Airport (CCIA) Rehabilitate Terminal Apron Phase III and East General Aviation Apron Phase IV projects, effective upon issuance of notice to proceed, with funding available in the Airport Capital program by acceptance of the grant and; transferring $1,049,486 as a 10% grant match from the unreserved fund balance of the Airport Operational Fund.
|